Introduction
1.
This is the 21st Monthly Environmental Monitoring
and Audit (EM&A) Report prepared by the Environmental Team (ET), Cinotech Consultants Ltd., for Contract No. HY/2019/13 “Central
Kowloon Route – Buildings, Electrical and Mechanical Works”. This report summarises
the monitoring results and audit findings of the EM&A programme under the
issued EP No. EP-457/2013/D, and in accordance with the EM&A programme in the
Ho Man Tin area
during the reporting period from 1 September 2025 – 30 September
2025.
2.
The major site activities
undertaken in the reporting month included:
l
ABWF works
Environmental
Monitoring Works
3.
Environmental monitoring
for the Project was performed in accordance with the EM&A Manual, and the monitoring results were checked and reviewed.
Joint weekly site inspections with the representative of ET, the Engineer
Representative and the Contractor for Contract No. HY/2019/13 were
conducted on 2, 9, 16, 23 & 30 September 2025,
whereas a joint site inspection with the representative of IEC was conducted on
16 September 2025. The implementation of the environmental
mitigation measures, Event and Action Plans and environmental complaint
handling procedures was also checked.
4.
A summary of the non-compliance (exceedance) during the reporting month (September 2025) and the investigation results and/or follow-up actions
is provided below:
Air Quality
Monitoring
l No Action/Limit Level exceedance for 1-hour TSP was recorded.
l No Action/Limit Level exceedance for 24-hour TSP was recorded.
l
No Action Level exceedance for construction noise was recorded.
l No Limit Level exceedance for construction noise was
recorded.
l
No non-conformity for landscape
and visual was recorded.
Complaint Handling,
Prosecution and Public Engagement
5.
Summary of complaint/summons/prosecution in the
reporting month is tabulated in Table I.
Table I Summary
of Complaint/Summons/Prosecution in the Reporting Month
|
Event
|
Event Details
|
Follow-up/ Remedial Actions
|
Status/ Remarks
|
|
Number
|
Brief Description
|
|
Complaints Received
|
0
|
-
|
-
|
-
|
|
Notification of Summons and
Prosecutions Received
|
0
|
-
|
-
|
-
|
Reporting
Changes
6.
There were no reporting
changes during the reporting month.
Future
Key Issues
7.
The key works or activities will be
anticipated in the coming two months are as
follows:
l
ABWF works
1.2
The Environmental Impact
Assessment Report for Central Kowloon Route – Design and Construction (Register
No.: AEIAR-171/2013) was approved under the Environmental Impact Assessment
Ordinance (EIAO) on 11 July 2013. An Environmental Permit (EP No.: EP-
457/2013) was issued on 9 August 2013. Variations of Environmental Permit (VEP)
was subsequently applied and an EP (EP No. EP-457/2013/C) was issued on 16
January 2017. The latest EP (EP No. EP-457/2013/D) was issued by Environmental
Protection Department (EPD) on 15 June 2021.
1.3
The construction of the CKR had
been divided into different sections. This Contract No. HY/2019/13 – Central
Kowloon Route – Buildings, Electrical and Mechanical Works (“The Project”) will
include the architectural, civil and structural construction works of Yau Ma Tei Ventilation Building (YVB), Ho Man Tin Ventilation Building
(HVB), Kai Tak Ventilation Building (KVB) and Central Kowloon Route
Administration Building (ADB) for the CKR. The
landscaping and electrical and mechanical (E&M) works within the building
sites will be involved as well.
1.4
Cinotech Consultants Limited was assigned as the Environmental Team (ET) to undertake the EM&A works for the
Project. The construction of this Contract was commenced on 12th December
2020.
1.5
The construction work on the Ho
Man Tin area under Contract no. HY/2018/08 Central Kowloon Route – Central
Tunnel was completed on 31 December 2023. Contract no. HY/2019/13 Central
Kowloon Route – Buildings, Electrical and Mechanical Works in Ho Man Tin area
was then commenced on 1 January 2024 and took over the site of Ho Man Tin area.
1.6
The
baseline report for environmental monitoring was used the same as the
HY/2018/08 on the Ho Man Tin area. The baseline air quality and noise
monitoring were conducted in January 2018. The baseline monitoring results are
presented in the Approved Baseline Monitoring Reports in accordance with
EP-457/2013/C Condition 3.3 under Contract no. HY/2014/09 Central Kowloon Route
– Ho Man Tin Access Shaft.
1.7
This is
the 21st
Monthly EM&A Report, which summarises the
impact monitoring results and audit findings for the EM&A programme in the Ho Man
Tin area
during the reporting period from 1 September 2025 – 30 September
2025. The Ho Man
Tin area site layout plan for the Project is shown in Figure 1.
1.8
Different Parties with
different levels of involvement in the project organisation include:
l Project Proponent – Highways Department (HyD)
l Engineer Representative (ER) – Arup – Mott MacDonald Joint Venture (AMMJV)
l Environmental Team (ET) – Cinotech
Consultants Limited (Cinotech)
l Independent Environmental Checker (IEC) – Environmental Resources
Management – Hong Kong Limited (ERM)
l
Contractor – Gammon Construction Limited (GCL)
1.9
The key contacts of the
Project are shown in Table 1.1.
Table 1.1 Key Project Contacts
|
Party
|
Role
|
Contact Person
|
Phone No.
|
|
AMMJV
|
Engineer
Representative
|
Mr. Tommy
Wong
|
3695 0419
|
|
Cinotech
|
Environmental
Team
|
Ms.
Betty Choi
|
2151 2072
|
|
ERM
|
Independent
Environmental Checker
|
Ms.
Mandy To
|
2271 3113
|
|
GCL
|
Contractor
|
Mr.
William Chan
|
5408 3045
|
1.11
The construction programme is
presented in Appendix M.
1.12
The major site activities
undertaken in the reporting month included:
l
ABWF works
1.13
The EM&A programme requires
air quality monitoring, noise monitoring, landscape
and visual monitoring, and environmental site audit.
The EM&A requirements for each parameter are described in the following
sections, including:
l Environmental requirements and mitigation measures, as recommended
in the EM&A Manual under the EP.
1.15
All permits/licenses obtained for the Project are summarised
in Table 1.2.
Table 1.2 Summary
of Environmental Licensing and Permit Status
|
Permit / License No.
|
Valid Period
|
Status
|
|
From
|
To
|
|
Environmental Permit (EP)
|
|
EP-457/2013/D
|
15
Jun 2021
|
N/A
|
Valid
|
|
Notification of Construction Works under
Air Pollution Control Ordinance (APCO)
|
|
457345
|
19
Jun 2020
|
End
of Project
|
Valid
|
|
Billing Account for Construction Waste
Disposal
|
|
7037679
|
26
Jun 2020
|
N/A
|
Valid
|
|
Registration of Chemical Waste Producer –
Ho Man Tin
|
|
5213-236-G2347-61
|
28
Nov 2023
|
N/A
|
Valid
|
|
Wastewater Discharge Licence - Ho Man Tin
|
|
WT10002215-2023
|
2
Feb 2024
|
31
Jan 2029
|
Valid
|
|
Construction Noise Permit - Ho Man Tin
|
|
GW-RE0352-25
|
14 Apr 2025
|
13 Oct 2025
|
Valid
|
2
2.1
According to the EM&A
Manual under the EP, 1-hour and 24-hour TSP monitoring were conducted to
monitor the air quality for this Project. For regular impact monitoring, a
sampling frequency of at least once every six days is required at all of the
monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the
sampling frequency of at least three times in every six days shall be
undertaken when the highest dust impact occurs. Appendix A shows the
established Action/Limit Levels for the environmental monitoring works.
2.2
Only one designated monitoring
station was selected for the 1-hour and 24-hour TSP impact dust monitoring
programme. Both dust monitoring stations were conducted at the designated
monitoring station (M-A3).
2.3
Table 2.1 describes the air quality monitoring locations, which are also
depicted in Figure 3.
Table 2.1 Locations for Air Quality
Monitoring
|
Monitoring Stations
|
Locations
|
Location of Measurement
|
|
M-A3
|
S.K.H. Tsoi Kung Po
Secondary School
|
Rooftop
(above 3/F) Area
|
2.4
Table 2.2 summarises the equipment used in the impact air monitoring
programme. Copies of calibration certificates are attached in Appendix B.
Table 2.2 Air Quality Monitoring
Equipment
|
Equipment
|
Model and Make
|
Serial No.
|
Quantity
|
|
Calibrator
|
TISCH TE-5025A
|
3864
|
1
|
|
1-hour TSP Dust Meter
|
Dust Monitor System
OC-9200
|
OC20210316224101
|
1
|
|
High Volume Sampler
|
TE-5170 c/w of TSP
sampling inlet
|
2204
|
1
|
|
Wind Anemometer
|
C-OC-9200-wind
|
OC20210316224101
|
1
|
2.5
Table 2.3 summarises the monitoring parameters and frequencies of impact dust
monitoring for the whole construction period. The air quality monitoring
schedule for the reporting month is shown in Appendix D.
Table 2.3 Impact Dust Monitoring
Parameters, Frequency and Duration
|
Parameters
|
Frequency
|
|
1-hour TSP
|
Three times / 6 days
|
|
24-hour TSP
|
Once / 6 days
|
1-hour TSP
Monitoring
Measuring Procedures
2.6
The measuring procedures of the
1-hour dust meters were in accordance with the Manufacturer’s Instruction
Manual as follows: (OC-9200 Dust Monitoring System)
l
The 1-hour dust meter is placed
at least 1.3 meters above ground.
l
Set POWER to “ON” and make sure
that the battery level was not flash or in low level.
l
Allow the instrument to stand
for about 3 minutes and then the cap of the air sampling inlet has been
released.
l
Push the knob at MEASURE
position.
l
Set time/mode setting to [BG]
by pushing the time setting switch. Then, start the background measurement by
pushing the start/stop switch once. It
will take 6 sec. to complete the background measurement.
l
Push the time setting switch to
change the time setting display to [MANUAL] at the bottom left of the liquid
crystal display.
l
Finally, push the start/stop
switch to stop the measuring after 1 hour sampling.
l
Information such as sampling
date, time, count value and site condition were recorded during the monitoring
period.
Maintenance/Calibration
2.7
The following
maintenance/calibration was required for the direct dust meters:
l
Check and calibrate the meter
by HVS to check the validity and accuracy of the results measured by direct
reading method at 2-month intervals throughout all stages of the air quality
monitoring.
24-hour TSP
Monitoring
Instrumentation
2.8
High volume (HVS) samplers
(Model TE-5170), completed with appropriate sampling inlets, were employed for
24-hour TSP monitoring. The sampler was
composed of a motor, a filter holder, a flow controller and a sampling inlet
and its performance specification complied with that required by USEPA Standard
Title 40, Code of Federation Regulations Chapter 1 (Part 50). Moreover, the HVS
also met all the requirements in section 2.5 of the updated EM&A Manual.
2.9
The positioning of the HVS
samplers are as follows:
l
A horizontal platform was
provided with appropriate support to secure the samplers against gusty wind.
l
No two samplers were placed
less than 2 meters apart.
l
The distance between the
sampler and an obstacle, such as buildings, was at least twice the height that
the obstacle protrudes above the sampler.
l
A minimum of 2 meters of
separation from walls, parapets and penthouses was required for rooftop
samples.
l
A minimum of 2 meters
separation from any supporting structure, measured horizontally was required.
l
No furnaces or incineration
flues were nearby.
l
Airflow around the sampler was
unrestricted.
l
The sampler was more than 20
meters from the drip line.
l
Any wire fence and gate, to
protect the sampler, should not cause any obstruction during monitoring.
Operating/analytical procedures for the operation of HVS
2.10
Operating/analytical procedures for the air quality monitoring are
highlighted as follows:
l
Prior to the commencement of
the dust sampling, the flow rate of the high volume
sampler was properly set (between 1.1 m3/min. and 1.4 m3/min.) in accordance
with the manufacturer’s instruction to within the range recommended in USEPA
Standard Title 40, CFR Part 50.
l
For TSP sampling, fiberglass
filters have a collection efficiency of > 99% for particles of 0.3μm
diameter were used.
l
The power supply was checked to
ensure the sampler worked properly. On sampling, the sampler was operated for 5
minutes to establish thermal equilibrium before placing any filter media at the
designated air monitoring station.
l
The filter holding frame was
then removed by loosening the four nuts and a weighted and conditioned filter
was carefully centred with the stamped number upwards, on a supporting screen.
l
The filter was aligned on the
screen so that the gasket formed an airtight seal on the outer edges of the
filter. Then the filter holding frame
was tightened to the filter holder with swing bolts. The applied pressure
should be sufficient to avoid air leakage at the edges.
l
The shelter lid was closed and
secured with the aluminium strip.
l
The timer was then programmed.
Information was recorded on the record sheet, which included the starting time,
the weather condition and the filter number (the initial weight of the filter
paper can be found by using the filter number).
l
After sampling, the filter was
removed and sent to the HOKLAS laboratory (High Precision Chemical Testing
Ltd.) for weighing. The elapsed time was
also recorded.
l
Before weighing, all filters
were equilibrated in a conditioning environment for 24 hours.
l
The conditioning environment
temperature should be between 25°C and 30°C and not vary by more than ±3°C; the
relative humidity (RH) should be < 50% and not vary by more than ±5%. A
convenient working RH is 40%.
Maintenance/Calibration
2.11 The following maintenance/calibration was required for the HVS:
l
The high-volume motors and
their accessories were properly maintained. Appropriate maintenance such as
routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power
supply are in good working condition.
l
High volume samplers were
calibrated at bi-monthly intervals using TE-5025A Calibration Kit through\hout all stages of the air quality monitoring.
2.12
All 1-hour TSP monitoring was
conducted as scheduled in the reporting month.
2.13
No Action/Limit Level
exceedance of the 1-hour TSP monitoring was recorded.
2.14
All 24-hr TSP monitoring was
conducted as scheduled in the reporting month, except the monitoring scheduled
for 24 September 2025 was cancelled and reschedules to 25 September 2025 due to
the issuance of Hurricane Signal No. 10 on the original date. The monitoring schedule for the reporting month
is shown in Appendix D.
2.15
No Action/Limit Level
exceedance of the 24-hour TSP monitoring was recorded.
2.16
The weather information for the
reporting month is summarised in Appendix C.
2.17
The monitoring data and
graphical presentations of 1-hour and 24-hour TSP monitoring results are shown
in Appendix E and Appendix F, respectively.
2.18
No exceedance was recorded for
the air quality monitoring. The summary of the exceedance record in the reporting
month is shown in Appendix H.
2.20 According to our field observations during the monitoring, the major
dust sources identified at the designated air quality monitoring stations are
road traffic dust, exposed site area and open stockpiles, excavation works and
site vehicle movements.
3
3.1
According to EM&A Manuals
under the EP, construction noise monitoring was conducted to monitor the
construction noise arising from the construction activities. The regular
monitoring frequency for each monitoring station shall be on a weekly basis,
and one set of measurements between 0700 and 1900 hours on normal weekdays. Appendix
A shows the established Action and Limit Levels for the environmental
monitoring works.
3.2
Only one designated monitoring
station was selected for the noise monitoring programme. Noise monitoring was
conducted at the designated monitoring station (M-N3).
3.3
Table 3.1 describes the noise
monitoring locations, which are also depicted in Figure 3.
Table 3.1 Noise
Monitoring Stations
|
Monitoring Stations
|
Locations
|
Location of Measurement
|
|
M-N3
|
S.K.H. Tsoi Kung Po
Secondary School
|
Rooftop
(above 3/F) Area
|
3.4
Table 3.2 summarises the noise monitoring equipment. Copies of calibration
certificates are provided in Appendix B.
Table 3.2 Noise
Monitoring Equipment
|
Equipment
|
Model and Make
|
Serial No.
|
Quantity
|
|
Sound Calibrator
|
Hangzhou Aihua Instruments Co., Ltd. AWA6021A
|
1023064
|
1
|
|
Integrating Sound Level Meter
|
BSWA Technology BSWA 308
|
570188, 580238
|
2
|
3.5
Table 3.3 summarizes the monitoring parameters, frequency and total duration
of monitoring. The noise monitoring
schedule is shown in Appendix D.
Table 3.3 Noise
Monitoring Parameters, Frequency and Duration
|
Monitoring Stations
|
Parameter
|
Period
|
Frequency
|
Measurement
|
|
M-N3
|
L10(30 min.) dB(A)
L90(30 min.) dB(A)
Leq(30 min.) dB(A)
|
0700-1900 hrs on normal weekdays
|
Once per week
|
Façade
|
3.6
The procedures for noise
monitoring were as follows:
l
The Sound Level Meter was set
on a tripod at a height of 1.2 m above the ground.
l
The battery condition was
checked to ensure the correct functioning of the meter.
l
Parameters such as frequency
weighting, the time weighting and the measurement time were set as follows:
— frequency weighting :
A
— time weighting :
Fast
— time measurement :
30 minutes
l
Prior to and after each noise
measurement, the meter was calibrated using a Calibrator for 94.0 dB at 1000
Hz. If the difference in the calibration
level before and after measurement was more than 1.0 dB, the measurement would
be considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
l
The wind speed was frequently
checked with the portable wind meter.
l
At the end of the monitoring
period, the Leq, L90 and L10
were recorded. In addition, site conditions and noise sources were recorded on
a standard record sheet.
l
Noise measurement was paused
temporarily during periods of high intrusive noise if possible and observation
was recorded when intrusive noise was not avoided.
l
Noise monitoring was cancelled
in the presence of fog, rain, and wind with a steady speed exceeding 5 m/s, or
wind with gusts exceeding 10 m/s.
Maintenance and Calibration
3.7
The microphone head of the
sound level meter and calibrator were cleaned with a soft cloth at quarterly
intervals.
3.8
The sound level meter and
calibrator were checked and calibrated at yearly intervals.
3.9
Immediately prior to and
following each noise measurement the accuracy of the sound level meter shall be
checked using an acoustic calibrator generating a known sound pressure level at
a known frequency. Measurements may be accepted as valid only if the calibration
levels from before and after the noise measurement agree to within 1.0 dB.
3.11 The Baseline Noise Level and the Noise Limit Level at the designated
noise monitoring station are presented in Table 3.4.
Table 3.4 Baseline Noise Level and Noise Limit Level for
Monitoring Stations
|
Monitoring
Stations
|
Baseline Noise Level, dB (A)
|
Noise
Limit Level, dB (A)
|
|
M-N3
|
67.7(1)
(at 0700 –
1900 hrs on normal weekdays)
|
70(*)
(at 0700 –
1900 hrs on normal weekdays)
|
(*) Noise Limit Level is 65 dB(A) during school
examination periods.
Note (1): The noise level due to the construction
work (CNL) was calculated by the following formula:
CNL = 10 log
(10MNL/10 – 10BNL/10)
Remarks: MNL =
Measured Noise Level, BNL = Baseline Noise Level
3.12 No Action Level and Limit
Level exceedance was recorded. The summary of the exceedance record in the reporting
month is shown in Appendix H.
3.13 Noise monitoring results and graphical presentations are shown in Appendix
G.
3.14
Site audits were carried out on a weekly basis to monitor and audit the
timely implementation of construction noise mitigation measures within the site
boundaries of this Project. The summary
of site audits is shown in Table 6.1 of this report.
3.15 According to our field
observations during the monitoring, the major noise sources identified at the
designated noise monitoring stations are road traffic noise, site vehicle
movement, excavation works and daily school activities.
4
4.1
Waste generated from this
Project includes inert construction and demolition (C&D) materials and
non-inert C&D materials. Inert C&D waste includes soil, broken rock,
broken concrete and building debris, while non-inert C&D materials are made
up of C&D waste which cannot be reused or recycled and has to be disposed
of at the designated landfill sites.
4.2
The quantities of different
types of waste generated in the reporting month are summarised in Table 4.1. Details of the amount of waste generated by the major site
activities of this Project during the reporting month are shown in Appendix L.
Table 4.1 Quantities
of Waste Generated from the Project
|
Quantity
|
|
|
Inert C&D Materials
|
Non-inert C&D Materials
|
|
Reporting
Period
|
Total
Quantity
Generated
(in
'000m3)
|
Disposed
as
Public
Fill (in '000m3)
|
Others,
e.g.
general
refuse (in '000m3)
|
Metals
(in
'000kg)
|
Paper/cardboard
Packaging
(in
'000kg)
|
Plastics
(in
'000kg)
|
Chemical
waste (in '000kg)
|
|
Sep 2025
|
0.000
|
0.000
|
0.000
|
0
|
0
|
0
|
0
|
4.3
Site audits were carried out on
a weekly basis to monitor and audit to ensure that proper storage, transportation,
and disposal practices of waste materials generated during construction
activities, such as construction and demolition (C&D) materials and general
refuse, are being implemented. The summary of site audits is
shown in Table 6.1 of this report. The implementation status of the
waste/chemical management measures in the reporting period is summarised in Appendix J.
5
landscape and visual
5
5.1
According
to the EM&A Manual, site audits would be undertaken
during the construction phase of the Project to check that the proposed
landscape and visual mitigation measures are properly implemented and
maintained as per their intended objectives. Site inspections of the
implementation of landscape and visual mitigation measures would be
undertaken at least once every two weeks during the construction period.
5.2
Bi-weekly inspection of the
implementation of landscape and visual mitigation measures within the site
boundaries of this Project was conducted on 2, 16, & 30 September
2025. The implementation status of the landscape
and visual mitigation measures in the reporting period is summarised in Appendix J. The summary of observations and
recommendations made for landscape and visual mitigation measures during site
audits is shown in Table 6.1 of this report.
5.3
No non-compliance with the
landscape and visual impact was recorded in the reporting month.
5.4
Should non-compliance of the landscape and visual impact occur, action
in accordance with the action plan presented in Appendix I shall be
performed.
6
6.1
Site audits were carried out on
a weekly basis to monitor the timely implementation of proper environmental
management practices and mitigation measures in the Project site.
6.2
Site audits for Contract No.
HY/2019/13 were conducted on 2, 9, 16, 23 & 30 September 2025 in the reporting month. Joint site inspection with the representative of IEC was conducted on 16 September
2025. No
non-compliance was observed during the site audit.
6.3
According to the Environmental
Permit, the approved EIA Report (Register No.: AEIAR-171/2013), and
the EM&A Manual of the Project, the mitigation measures detailed in the
documents are recommended to be implemented during the construction phase. An Environmental Mitigation Implementation
Schedule (EMIS) is provided in Appendix J.
6.4
The ET weekly site inspections
were carried out during the reporting month, and the observations and follow-up
actions in the Ho Man Tin Area are summarised in Table 6.1.
Table 6.1 Observations and Recommendations of Site
Inspections
|
Parameters
|
Date
|
Observations
|
Follow-up
Actions
|
|
Water Quality
|
N/A
|
No environmental deficiency was identified in the reporting period.
|
N/A
|
|
Air Quality
|
N/A
|
No environmental deficiency was identified in the reporting period.
|
N/A
|
|
Noise
|
N/A
|
No environmental deficiency was identified in the reporting period.
|
N/A
|
|
Waste / Chemical
Management
|
N/A
|
No environmental deficiency was identified in the reporting period.
|
N/A
|
|
Land
Contamination
|
9 Sep 2025
|
Drip tray should be provided for chemical.
|
Chemical has been removed.
|
|
Landscape and Visual
|
N/A
|
No environmental deficiency was identified in the reporting period.
|
N/A
|
|
Permits /Licences
|
N/A
|
No environmental deficiency was identified in the reporting period.
|
N/A
|
6.5
The Event Action Plans for air
quality, noise and landscape and visual are presented in Appendix I.
Air Quality Monitoring
l No Action/Limit Level exceedance for 1-hour TSP was recorded.
l No Action/Limit Level exceedance for 24-hour TSP was recorded.
Noise Monitoring
l No Action
Level exceedance for noise was recorded.
l No Limit Level exceedance for noise was recorded.
Landscape and Visual
Monitoring
l No non-conformity for landscape and visual was recorded.
6.6
No environmental complaint and environmental warnings, notifications of
summons and successful prosecutions were received in the reporting month.
6.7
The summary of environmental
complaint, warning, summons and notification of successful prosecution for the
Project is presented in Appendix K.
6.8
Status of required submission
under EP-457/2013/D during the reporting period is summarised in Table 6.2.
Table 6.2 Status of Required Submission under
Environmental Permit
|
EP Condition
(EP-457/2013/D)
|
Submission
|
Submission Date
|
|
Condition
3.4
|
Monthly
EM&A Report (August
2025)
|
11 September 2025
|
7
future Key issues
7
7.1
Major site activities undertaken for the coming two months include:
l
ABWF works
7.2
Key environmental issues in the
coming two months include:
l Stockpile accumulation on-site;
l Water spraying for dust generating activities and on haul road;
l Wastewater and runoff discharge from site;
l Coverage of open manholes to avoid dirty runoff to drainage system;
l Noise from operation of the equipment, especially for excavation
works and machinery onsite;
l Accumulation of general refuse and construction waste on-site;
l Proper storage of construction materials on-site; and
l Storage of chemicals/fuel and chemical waste/waste oil on-site.
7.3
The tentative environmental monitoring schedules for next month are
shown in Appendix D.
8
8.1
This
is the 21st Monthly EM&A Report, which presents the EM&A works undertaken in the Ho Man Tin area during
the reporting month from 1 September 2025 – 30 September 2025 in accordance with the EM&A Manual and the requirements under the EP.
Air Quality Monitoring
8.2
All 1-hr TSP monitoring was conducted as scheduled in the reporting
month.
8.3
No Action/Limit Level exceedance was recorded for all 1-hour TSP
monitoring in the reporting month.
8.4
All 24-hr TSP monitoring was
conducted as scheduled in the reporting month, except the monitoring scheduled
for 24 September 2025 was cancelled and reschedules to 25 September 2025 due to
the issuance of Hurricane Signal No. 10 on the original date.
8.5
No Action/Limit Level exceedance was recorded for all 24-hour TSP
monitoring in the reporting month.
Construction Noise
Monitoring
8.6
All construction noise monitoring was conducted as scheduled in the
reporting month.
8.7
No Action Level and Limit Level exceedance was recorded.
Landscape and visual
8.8
No
non-compliance was recorded in the reporting month.
Site Audit
8.9
5 ET joint weekly environmental
site inspections were conducted in the reporting month. Joint weekly site inspections with the representative of ET, the Engineer
Representative and the Contractor for Contract No. HY/2019/13 were conducted on
2, 9, 16, 23 &
30 September 2025, whereas a joint
site inspection with the representative of IEC was conducted on 16 September 2025. All environmental
deficiencies observed during site inspections were rectified by the Contractor.
Complaint, Notification of
Summons and Successful Prosecution
8.10
No environmental complaint, notifications of summons and successful
prosecutions were received in the reporting month.